MAKING PROGRESS ON NEW FIRE STATION 78
Construction continues on new Fire Station 78 in Studio City. Partition walls are currently being constructed and dry wall is being hung in the 2 story living area. Block wall work continues on the heavy apparatus bays and sub-contractors continue to install the mechanical, electrical, and plumbing components of the Fire Station.
Work continues on the 2 story portion of the Fire Station. Located downstairs will be the office, training room, community-conference room, kitchen, work rooms, storage rooms, and work-out room. Upstairs will be the dorms, locker rooms and restrooms.
Ground level view of the three light apparatus bays. Apparatus doors will be bi-parting aluminum doors.
Drywall being hung and steel stud partition walls being installed.
Workers continue to construct the CMU block walls for the heavy apparatus bays.




Completion of the Fire Station is still scheduled for early 2008.